What’s happened so far
Work is underway on Phase II of the Penn Avenue Reconstruction project. Since May 29, the city’s contractor has made progress on two sections.
Between Pacific and Atlantic they have:
• Finished pouring and saw-cutting the new roadway
• Restored driveway access to Aldi from Penn Ave. (Another short term closure will be needed when the driveway concrete is being poured and cured)
• Adjusted the work zone and barriers to establish a pedestrian walkway on the newly poured street segment
• Began excavating the sidewalk
Between Atlantic and Aiken they have:
• Shifted the work zone and channelizers
• Began demolition of the existing roadway
|