What’s coming in the next two weeks
Atlantic to Aiken
• Forming the new travel lane
• Pouring the curb and new travel lane
Traffic and Parking Changes
• People’s Natural Gas will be lowering a conflicting gas line at the Penn/Aiken Intersection overnight beginning Monday, July 13. Work is expected to take up to three nights. Westbound traffic will be detoured off of Penn around 8 p.m. and reopened to traffic by 6 a.m. the following morning.
• Pittsburgh Water will be replacing a lead service line on Penn Ave between Aiken and Atlantic overnight on Tuesday, July 14, within the same detour as the People’s Natural Gas closure above.
|